Emergency Semtech Maintenance on GRX Infrastructure – North America, Madison Data Center (GNOC-11260)

Scheduled Maintenance Report for Status - Sierra Wireless

Completed

The scheduled maintenance has been completed.
Posted Feb 27, 2026 - 05:38 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 27, 2026 - 04:01 UTC

Update

This maintenance will be postponed to the following date.
Start time: 2026-02-27 04:00 UTC
End time: 2026-02-27 08:00 UTC
The purpose and impact remains unchanged.
Posted Feb 26, 2026 - 04:01 UTC

Update

This maintenance will be postponed to the following date.
Start time: 2026-02-26 04:00 UTC
End time: 2026-02-26 08:00 UTC
The purpose and impact remains unchanged.
Posted Feb 25, 2026 - 01:21 UTC

Scheduled

Semtech will be doing maintenance on its GRX provider carrier’s link in Madison NAM data center as part of an initiative to improve network resiliency and efficiency. This work aligns with our commitment to providing best-in-class services with Semtech.

Impact: There will be no impact to services. This notification is being provided as the activity involves maintenance on GRX provider’s link. No network degradation is anticipated during the maintenance window.

Additional Information: Semtech engineers will be actively monitoring the network throughout the maintenance activity. Notifications will be sent prior to the start of the work and upon completion.
Posted Feb 18, 2026 - 14:40 UTC
This scheduled maintenance affected: SW Advanced (Data (NA)), SW Essentials3 (Data (NA)), SW Essentials1 (Data), SW Essentials2 (Data), SW Essentials4 (Data), SW Essentials5 (Data), and Enhanced Carrier Connectivity (NAM) / MSO (AT&T - Data, Verizon - Data, Jasper - Data, Rogers - Data, Sprint - Data, T Mobile - Data, Telenor - Data, Xpress (2G Airadigm) - Data).